PM FPX 3000 Assessment 3 Trip of a Lifetime PM-FPX3000 Principles of Project Management

PM FPX 3000 Assessment 3 Trip of a Lifetime PM-FPX3000 Principles of Project Management

 

Prof. Name:

Date

Version Control

1.0 Notes:

  • Initial project plan release.

2.0 Notes:

  • Completed project plan release.
  • Project Charter Budget adjustments.
  • WBS chart adjustments.

Project Charter

Project Title: Western Europe & Iceland Expedition
Project Start Date: 25/2019
Project Finish Date: 25/2019
Budget: $35,000.00

  • Cruise: $10,980.00
  • Flights: $7,383.00
  • Passports: $600.00
  • Transportation: $1,150.00
  • Excursions: $1,300.00
  • Souvenirs: $1,200.00
  • Meals: $1,250.00
  • Misc.: $200.00
  • Emergency Funds: $5,000.00
  • Unused Funds: $5,937.00

Project Manager: Dean M. Slocum

Project Objectives:

The four members of the Scott family will visit five countries within three weeks using a budget of $35,000. The plan will include a detailed itinerary with time and cost considerations for travel to the departing seaport, return trip, room and board, planned locations to visit, budget for individual activities, and a comprehensive cost breakdown.

Approach:

  • Documentation: The family will apply for passports before the trip to ensure smooth participation in the cruise.
  • Room and Board: The family will be on a cruise to reduce risk factors and accommodate their size. The cruise will provide room, board, food, and a general trip timeline.
  • Travel to/from Airport: Bill’s brother will drive the family to Miami International Airport (MIA) from their home in Pembroke Pines, FL, avoiding long-term parking costs. He will also pick them up after the trip.
  • Travel to Departing Seaport in Lisbon, Portugal: The family will use a dedicated shuttle to reach the commercial port of Doca de Alcantara, where they will board the cruise liner, check in, and locate their suite.
  • Travel to Airport from Seaport in Reykjavik, Iceland: The family will take a dedicated shuttle from the seaport to the airport, where they will check in and proceed to their designated departure gate.
  • Timeline and Budget: This information will be presented to the family in a chronological order within an Excel spreadsheet, alongside a budget spreadsheet showing the distribution of funds.

Stakeholder Register

Stakeholder Identification

Name Role Position Contact Information
Dean Slocum Project Manager Oversees all aspects of project. Phone, Email, SMS
Bill Scott Father, Sponsor, Customer Primary contact in establishing project details. Phone, Email, SMS
Alexandra Scott Mother, Sponsor, Customer Secondary contact in establishing project details. Phone, Email
Nick Scott Son, Customer Provides input. N/A
Corey Scott Son Provides input. N/A

Stakeholder Assessment

Requirements Communication Needs Frequency of Communication Expectations Influence on the Project Interest and Power
Book Flights High Weekly $7,383.00 High High
Book Cruise High Weekly $10,980.00 High High
Passports High Weekly $600.00 High High
Transportation Medium Weekly $1,500.00 Medium Medium
Excursions High Weekly $5,000.00 High High
Souvenirs Low Weekly $1,000.00 Medium Medium
Emergency Funds High Weekly $1,000.00 Low Low

Stakeholder Classification

Order a similar paper

Get the results you need


Interest Power Classification
High High Manage Closely
Medium