PM FPX 5333 Assessment 2 Earned Value Analysis Report PM-FPX5333 Project Budgeting, Procurement, and Quality
Prof. Name:
Date
Introduction
NearlyFree.com is currently managing a project that has surpassed its initial budget of $25,000. The project is 43% complete, and the firm has acknowledged its shortcomings and sought our project management services. A detailed examination of the project’s financial statements reveals that the earned value is under-budgeted. The project’s objective is to develop and implement an automated web-based training system for new employees, aimed at reducing workload and minimizing the personnel resources needed for New Employee Orientation (NEO) training.
The project scope includes a 92-day timeline with an approved budget of $22,300. This report provides a review of the earned value technique, assesses the project’s success, and performs earned value calculations to facilitate an effective turnaround.
Earned Value Technique
Earned Value (EV) is a method used to monitor a project’s plan, actual work, and the value of work completed to determine if the project is on track. It indicates how much of the budget and time should have been utilized based on the amount of work completed. Project control is conducted against the cost baseline using the Earned Value technique, which involves calculating and reporting several variables based on actual progress.
Inputs:
- Earned Value (EV) represents the actual progress of the task up to the date of analysis.
- Planned Value (PV) is the planned expenditure of funds up to the date of analysis, derived from the project schedule.
- Actual Cost (AC) is the actual expenditure of funds up to the date of analysis.
Calculations:
- Cost Variance (CV) measures the amount the project is above or below budget at the point of analysis.
- Cost Performance Index (CPI) indicates the project’s performance relative to the overall budget.
- Schedule Variance (SV) measures how much the project is ahead or behind schedule.
- Schedule Performance Index (SPI) assesses how close the project is to the schedule relative to the overall project size.
Earned Value (EV) / Budget Cost of Work Performed (BCWP)
Earned Value reflects the percentage of the total effort or resources expended, which can be measured in completed units or hours of labor. It is also known as the Budget Cost of Work Performed (BCWP). The current BCWP for NearlyFree.com’s project is $12,373.95.
Planned Value (PV) / Budget Cost of Work Schedule (BCWS)
Planned Value represents the approved value of work scheduled to be completed by a specific time. It is calculated before the work begins and serves as a baseline. This value outlines the expected extent of activities and costs. It is also referred to as the Budget Cost of Work Schedule (BCWS). The current BCWS for the project is $20,453.95.
Actual Cost (AC) / Actual Cost of Work Performed (ACWP)
Actual Cost refers to the recorded cost for work completed during a specified time. This cost reflects the actual expenditure versus the budget estimates and is also known as Actual Cost of Work Performed (ACWP). The current ACWP for the project is $16,373.95.
Schedule Variance (SV)
Schedule Variance indicates whether a project schedule is ahead or behind. The formula for calculating schedule variance is:
Schedule Variance = Earned Value (EV) – Planned Value (PV)
Schedule Variance = $12,373.95 – $20,453.95
Schedule Variance = -$8,080.00
A schedule variance of -$8,080 signifies that the project is behind schedule.
Cost Variance (CV)
Cost Variance compares the initial budget with actual expenditures. It helps track financial progress as the project moves forward. The formula for cost variance is:
Cost Variance = Earned Value (EV) – Actual Cost (AC)
Cost Variance = $12,373.95 – $16,373.95
Cost Variance = -$4,000.00
A cost variance of -$4,000 indicates that the project is under budget, with the ideal variance being zero or positive.
Schedule Performance Index (SPI)
The Schedule Performance Index measures how close the project is to its scheduled completion. The formula for calculating SPI is:
Schedule Performance Index = Earned Value (EV) / Planned Value (PV)
Schedule Performance Index = $12,373.95 / $20,453.95
Schedule Performance Index = 0.60
An SPI of 0.60 means the project is behind schedule, as an SPI less than 1 indicates a delay.
Cost Performance Index (CPI)
The Cost Performance Index measures the financial effectiveness